State of Alaska Department of Transportation and Public Facilities (DOT&PF)
Notice to Being Engineering and Environmental Studies/Request for Public Comments
Sheep Creek Road and West Tanana Drive Roundabout (CMAQ)
NFHWY00902/0002(549)
The Alaska Department of Transportation and Public Facilities (DOT&PF) proposes to construct a single-lane roundabout at the Sheep Creek Road and West Tanana Drive (from here on referred to as, Sheep Creek Rd and W Tanana Dr) intersection in Fairbanks, Alaska. The project is located in Township 1 South, Range 2 West, and Section 1 of the Fairbanks Meridian. The purpose of this project is to improve safety, drainage, air quality, and reduce wait times for turning traffic movements at this intersection. To accomplish this purpose, the existing tee intersection would be replaced with a single-lane roundabout.
Proposed project elements include:
- Replace illumination around the intersection
- Update roadside hardware to include signing, signalization and illumination.
- Improve drainage in and around the intersection
- Improve parking facilities near the intersection
- Connect existing recreation trails systems with future trail network planned for the Gold Hill Rd area by extending walking path across intersection and along the north side of Sheep Creek Rd to Gold Hill Rd
Material sites for this project are expected to be contractor furnished.We are currently working on conceptual designs, engineering, and environmental studies, as well as soliciting public comments. Construction is currently planned for summer 2028.
View the project website here: https://dot.alaska.gov/nreg/sheepcreek-tanana/
DOT&PF requests information and comments on resources in the project area that may be affected including historic properties, archaeological sites, wetlands, and floodplain encroachment. The following Executive Orders (EO) apply:
EO 11990, Notice of Wetland Involvement
EO 11593, Protection and Enhancement of the Cultural Environment
EO 11988, Floodplain Management
EO 13112, Invasive Species, as amended by 13751
Please submit comments by November 9th, 2026 to:
Ethan Graetz, P.E.
Engineering Manager
2301 Peger Road, Fairbanks AK 99709-5316
Telephone: (907) 451-2281
Text Telephone (TDD): 771 or 1-800-770-8973
Email: ethan.graetz@alaska.gov
The environmental review, consultation, and other actions required by the applicable Federal environmental laws for this project are being, or have been, carried out by the DOT&PF pursuant to 23 U.S.C 327 and a Memorandum of Understanding dated April 13, 2023, and executed by FHWA and DOT&PF.
It is the policy of DOT&PF that no one shall be subject to discrimination on the basis of race, color, national origin, sex, age, or disability, regardless of the funding source, including Federal Transit Administration, Federal Aviation Administration, Federal Highway Administration, Federal Motor Carrier Safety Administration and State of Alaska funds. Title VI Nondiscrimination Policy: dot.alaska.gov/tvi_statement.shtml. To file a complaint, visit dot.alaska.gov/cvlrts/titlevi.shtml.