Notice of Application for State Air Quality Permit AQ0272MSS04, Hilcorp North Slope, LLC’s Lisburne Production Center

 

Hilcorp North Slope, LLC

Lisburne Production Center

The Alaska Department of Environmental Conservation (ADEC) has made a preliminary decision to approve Hilcorp North Slope, LLC’s application for Air Quality Control Minor Permit AQ0272MSS04 for the Lisburne Production Center.  

Applicant:      Hilcorp North Slope, LLC

                        3800 Centerpoint Drive, Suite 1400

                        Anchorage, AK 99503

Location:        Latitude 70º 17' 6.3" North; Longitude 148º 25' 54.3" West
                       

Activity:          Hilcorp North Slope, LLC applied for a minor permit under 18 AAC 50.508(6) to revise conditions in a Title I permit.

Emissions:      Change in emissions for stationary source is as follows: an increase of 1.01 tons of Volatile Organic Compounds (includes an increase of 0.175 TPY of HAPs) and an increase of 3.18 TPY of Particulate Matter. The emissions for nitrous oxides, carbon monoxide, and sulfur dioxide remain unchanged. The total annual potential emissions of regulated air pollutants, other than greenhouse gases, are 3,396.06 tons.

ADEC Preliminary Review:  Based on review of the application, ADEC drafted a preliminary permit decision for this project under AS 46.14 and 18 AAC 50.

Available Information:  Copies of the permit application(s), ADEC’s preliminary minor permit and technical analysis report (TAR) are available at the following offices:

ADEC Air Permits Program, 410 Willoughby Avenue, Suite 303, Juneau, Alaska 99801

ADEC Air Permits Program, 555 Cordova Street, Anchorage, AK 99501

These documents are also available at ADEC’s website at: http://dec.alaska.gov/Applications/Air/airtoolsweb/AirPermitsApprovalsAndPublicNotices/

Opportunity for Public Participation: Any interested person may present written statements relevant to the preliminary decision within 30 days after the first publication date. ADEC will consider all comments received and make any changes ADEC finds beneficial or necessary to assure compliance with 18 AAC 50 or state law. ADEC will issue a final decision to issue or deny the permit after the close of the public comment period.

ADEC complies with Title II of the Americans with Disabilities Act (ADA) of 1990. If you are a person with a disability who may need a special accommodation in order to participate in this public process, please contact ADA Coordinator Kristin Mabry, kristin.mabry@alaska.gov, 1-907-334-0884; Alaska Relay Service/TTY/TDD 1-800-770-8973; or dial 711 by the 15th day of this public comment period to ensure that any necessary accommodations can be provided.

Comments relevant to the preliminary minor permit may be submitted electronically via ADEC’s public notice site at https://dec.alaska.gov/Applications/Air/airtoolsweb/FormalComments, or to Peter Saengsudham by mail to 555 Cordova Street, Anchorage, AK 99501, or by email to peter.saengsudham@alaska.gov and dec.air.comment@alaska.gov. Comments must be received by close of public comments period at 11:59 p.m. Alaska time on November 24, 2025. Except for comments classified under AS 46.14.520, all public comments submitted during the public comment period can be viewed at https://dec.alaska.gov/Applications/Air/airtoolsweb/AirPermitsApprovalsAndPublicNotices  after the public comment period.

Attachments, History, Details

Attachments

None

Revision History

Created 10/22/2025 4:06:43 PM by jfrintala

Details

Department: Environmental Conservation
Category: Public Notices
Sub-Category:
Location(s): Statewide
Project/Regulation #: AQ0272MSS04
 
Publish Date: 10/22/2025
Archive Date: 11/25/2025
 
Events/Deadlines: