View

Notice

Share

Regulatory Commission of Alaska: Notice of Utility Tariff Filing (Chugach)

Notice of Utility Tariff Filing

The REGULATORY COMMISSION OF ALASKA (Commission) gives notice that Chugach Electric Association, Inc. (Chugach) filed TA577-8, its revenue requirement study and cost of service study based on the test year ended June 30, 2025. Chugach proposes an across-the-board interim and refundable rate increase of 4.66 percent for retail rates and decrease of 3.56 percent for wholesale rates, applicable to the current energy and demand charges, effective October 2, 2025. Chugach proposes revised permanent rates based on the outcome of the proposed revenue requirement study, cost of service study, and other minor rate design changes. Below is a sample of the current and proposed rates.

Rate Schedule

Current
Rate

Proposed
Interim Rate

Proposed
Permanent
Rate

Residential Customer Charge

$12.79

$12.79

$14.50

Residential Energy Charge

$0.15461

$0.16182

$0.16028

General Service (GS) Small Customer Charge

$19.46

$19.46

$19.00

GS Small Energy Charge

$0.14471

$0.15146

$0.15393

GS Large - Secondary Customer Charge

$31.99

$31.99

$25.00

GS Large - Secondary Energy Charge

$0.02839

$0.02971

$0.02970

GS Large - Secondary Demand Charge

$36.67

$38.38

$38.36

AWWU Replacement Energy Service

$0.02114

$0.02114

$0.01933

Chugach also proposes a new economic development rate (EDR) for commercial customers with new or incremental manufacturing loads with a maximum demand between 1,000 and 5,000 kW within two years of service commencement. Under the EDR, all charges will be the same as the applicable GS Large rate, with a declining demand charge discount, which begins at 20 percent in the first contract year and declines in equal increments annually until the final year. Other requirements apply.

This notice does not contain all requested revisions, and the Commission may approve a rate or classification that varies from those proposed. You may obtain more information about this filing by contacting Matthew Clarkson, Chief Legal Officer at Chugach, at P.O. Box 196300, Anchorage, AK 99519-6300; phone: (907) 762-4516. The complete filing is also available for inspection at the Commission's office, at 701 West Eighth Avenue, Suite 300, Anchorage, AK 99501; phone: (907) 276-6222, or may be viewed on the Commission’s website at http://rca.alaska.gov by typing “TA577-8” in the Find a Matter search box.

To comment on this filing, please file your comments by 5:00 p.m. on September 3, 2025, at the Commission address given above or via our website at:

https://rca.alaska.gov/RCAWeb/WhatsNew/PublicNoticesComments.aspx

Please reference TA577-8 and include a statement that you have filed a copy of the comments with Chugach at its address above. Individuals or groups of people with disabilities, who require special accommodations, auxiliary aids or service, or alternative communication formats, please contact Shelby Lopez at (907) 276-6222, toll-free at 1-800-390-2782, or TTY/Alaska Relay: 7-1-1 or 1 (800) 770-8973 or send a request via electronic mail to rca.mail@alaska.gov by August 27, 2025.

DATED at Anchorage, Alaska, this 20th day of August, 2025.

REGULATORY COMMISSION OF ALASKA

 

Joy Gordanier

Acting Advisory Section Manager

Leave a Comment

Attachments, History, Details

Revision History

Created 8/20/2025 8:44:38 AM by rtalabanzas

Details

Department: Commerce, Community, and Economic Development
Category: Public Notices
Sub-Category: Pipeline/Utilities
Location(s): Statewide
Project/Regulation #:
 
Publish Date: 8/20/2025
Archive Date: 9/4/2025
 
Events/Deadlines:
  • Public Comment Deadline
    9/3/2025 5:00pm