Regulatory Commission of Alaska: Notice of Utility Tariff Filing (Chugach)

Notice of Utility Tariff Filing

The REGULATORY COMMISSION OF ALASKA (Commission) gives notice that Chugach Electric Association, Inc. (Chugach) filed TA486-8, seeking to revise its distribution service fee schedule for raising or lowering facilities and special service installations. A sample of the current and proposed fees is listed below:

Service

Current Fee

Proposed Fee

Raising or Lowering of Facilities

 

 

Secondary Pedestal

$955.00

$960.00

Metal Street Light

$1,150.00

$1,155.00

Special Service Installations

 

 

New Underground Residential Service Joint Use Trench – Two Party Installation (without temporary Corflo Placement)

$11.70 per foot

$11.80 per foot

New Overhead Residential Service over 100 feet

$4.30 per foot

$4.40 per foot

Residential Service Pole

$1,200.00

$1,270.00

Down Guy Relocation, per Anchor

$1,220.00

$1,225.00

With TA486-8, Chugach also proposes to add an application fee for non-utility generation interconnection, for customers who install their own generation that will interconnect and operate in parallel with the Chugach system. The proposed application fee would cover the utility’s expense to review interconnection designs, conduct on-site inspections and process applications for installations with a name plate capacity up to 100kW. Chugach proposes an initial fee of $200.00 per application, which will be updated on an annual basis, consistent with its current schedule for distribution service fee updates.

This notice does not contain all requested revisions and the Commission may approve a rate or classification that varies from those proposed. You may obtain more information about this filing by contacting Nick Brodie, Senior Regulatory and Business Development Analyst at Chugach, at P. O. Box 196300, Anchorage, AK 99519-6300; phone: (907) 762-4512. The complete filing is also available for inspection at the Commission's office, at 701 West Eighth Avenue, Suite 300, Anchorage, AK 99501; phone: (907) 276-6222, or may be viewed on the Commission’s website at http://rca.alaska.gov by typing “TA486-8” in the Find a Matter search box.

To comment on this filing, please file your comments by 5:00 p.m. on May 1, 2020, at the Commission address given above or via our website at:

https://rca.alaska.gov/RCAWeb/WhatsNew/PublicNoticesComments.aspx

Please reference TA486-8 and include a statement that you have filed a copy of the comments with Chugach, at their address above or at info@chugachelectric.com. Individuals or groups of people with disabilities, who require special accommodations, auxiliary aids or service, or alternative communication formats, please contact Valerie Fletcher-Mitchell at (907) 276-6222, toll-free at 1-800-390-2782, or TTY/Alaska Relay: 7-1-1 or 1 (800) 770-8973, or send a request via electronic mail to rca.mail@alaska.gov by April 24, 2020.

DATED at Anchorage, Alaska, this 1st day of April 2020.

REGULATORY COMMISSION OF ALASKA

 

Becki Alvey

Tariff Section Manager

Attachments, History, Details

Revision History

Created 4/1/2020 3:36:07 PM by rtalabanzas

Details

Department: Commerce, Community and Economic Development
Category: Public Notices
Sub-Category: Pipeline/Utilities
Location(s): Statewide
Project/Regulation #:
 
Publish Date: 4/1/2020
Archive Date: 5/2/2020
 
Events/Deadlines:
  • Public Comment Deadline
    5/1/2020 5:00pm