NOTICE OF REVIEW
PROPOSED FINAL MODIFICATION OF AN
ALASKA POLLUTANT DISCHARGE ELIMINATION SYSTEM (APDES)
INDIVIDUAL PERMIT
Following the close of a 30-day public notice period, DEC has prepared an APDES proposed final modification for Golden Valley Electric Association Healy Power Plant. Prior to making the final decision to issue the final modified permit, DEC invites you to view the proposed final modified permit and associated documents. You can access the proposed final modified permit and associated documents at DEC’s Wastewater Discharge Authorization Program web page at: http://www.dec.state.ak.us/water/wwdp/index.htm
Proposed Final Modified Permit Review
Start Date: September 14, 2017
End Date: September 20, 2017
Permit No.: AK0022942
Proposed Modification:
The removal of Permit Sections 1.2.9 and 1.2.10, bottom ash transport water requirements, from the final GVEA Healy Power Plant permit, issued April 10, 2017.
Determination:
The ADEC has determined to modify the above listed individual permit.
DEC Contact: Marie Klingman
610 University Avenue
Fairbanks, AK 99709
(907) 451-2101
marie.klingman@alaska.gov