View

Notice

Share

RFP 2015-0500-2789 A Report on the Benefits and Disadvantages of Prototypical School Design and Construction in Alaska

Request For Proposals
RFP 2015-0500-2789
Date of Issue: September 19, 2015
A Report on the Benefits and Disadvantages of Prototypical School Design and Construction in Alaska

The Department of Education & Early Development, Division of School Finance, Facilities Section, is soliciting detailed proposals for a contractor to conduct research and submit a report that investigates the benefits and disadvantages of using prototypical designs for school construction throughout the state of Alaska. The Department will submit the report to the Alaska State Legislature not later than June 15, 2015.

Rhonda Biles

Procurement Officer

Rhonda.biles@Alaska.gov

 

 

 

 

Attachments, History, Details

Revision History

Created 9/19/2014 5:44:37 PM by rtroys
Modified 9/19/2014 5:47:02 PM by rtroys
Modified 9/19/2014 5:54:40 PM by rtroys
Modified 9/19/2014 5:55:35 PM by rtroys
Modified 9/22/2014 8:48:17 AM by rtroys
Modified 9/22/2014 2:22:20 PM by rtroys
Modified 9/30/2014 12:20:27 PM by rtroys
Modified 10/1/2014 12:50:30 PM by rtroys
Modified 10/1/2014 12:55:52 PM by rtroys
Modified 10/1/2014 12:56:24 PM by rtroys
Modified 10/10/2014 3:38:39 PM by rmbiles
Modified 10/16/2014 10:53:40 AM by rmbiles
Modified 10/16/2014 10:54:35 AM by rmbiles
Modified 10/20/2014 11:15:44 AM by rmbiles
Modified 10/20/2014 11:28:57 AM by rmbiles
Modified 10/20/2014 12:44:11 PM by rmbiles
Modified 10/20/2014 12:46:58 PM by rmbiles
Modified 10/20/2014 12:48:12 PM by rmbiles
Modified 10/31/2014 1:21:47 PM by rtroys
Modified 10/31/2014 2:15:09 PM by rtroys

Details

Department: Education and Early Development
Category: Procurement
Sub-Category:
Location(s): Statewide
Project/Regulation #: HB278, sec. 52
 
Publish Date: 9/19/2014
Archive Date: 11/11/2014
 
Events/Deadlines:
  • Issue RFP
    9/19/2014 12:00am
  • Pre proposal conference
    9/26/2014 1:30pm - 9/19/2014 3:30pm
  • Deadline for Receipt of Proposals
    10/27/2014 4:00pm
  • Notice of Intent to Award posted
    10/31/2014 5:00pm
  • State of Alaska issues contract
    11/12/2014 8:00am
  • Contract start
    11/13/2014 8:00am
  • First contractor work period
    11/13/2014 8:00am - 5/8/2015 5:00pm
  • Contractor submits Table of Contents
    3/16/2015 5:00pm
  • Review and Discussion Period
    5/8/2015 5:00pm - 5/22/2015 5:00pm
  • Contractor submits final report
    6/1/2015 5:00pm